C-Innovation recently received recognition for the crew’s hard work aboard the Island Intervention ensuring a project’s timeline remained on target and successful.
During the project, a leak was found after a section of coil tubing was connected and pressurized. Instead of sending out for another vessel to recover the unit and tighten the fittings, the C-Innovation team created a plan to carry two wrenches by HD06, a ROV, and utilized the T4 (arm extension) to tighten the fittings and stop the leak.